| PROJECT |
CLIENT |
DATE COMPLETED |
VALUE |
| Phokeng Bridge | Royal Bafokeng | Dec 2007 - Jul 2008 | R 1 300 000.00 |
| Building,Sports field,concrete fencing | Nepe Consulting Engineers | Feb – May 2004 | R 877 192.97 |
| Concrete bases and plinths | Xstrata Kroondal | 20 June - 20 July 2005 | R 250 000.00 |
| Roads at Royal Bafokeng Nation 16km JV | Royal Bafokeng Nation | 15 July - 15 December 2005 | R 11 000 000.00 |
| Upgrading of mogwase stadium | Makone Consulting Engineer | 2009-2010 | R 9 500 000.00 |
| Upgrading of Pedestrian Bridge at Rustenburg Noord | Bigen Africa on behalf of Rustenburg Municipality | July 2011-Nov 2011 | R 1 572 847.74 |
| Upgrading of bridge at Boitekong | Dimakotso Construction | 23 January2012 - 23March 2012 | R 1 036 504.48 |
| Upgrading Chaneng Road | Bafokeng Rasimone platinum mine | 07 March 2012 - 29 June 2012 | R 2 978 188.29 |
| Upgrading of internal road in Kroonstad | Makone Consulting Engineers | 04 September 2012 - 30 March 2013 | R 6 000 000.00 |
| Upgrading of internal road at Tlapa East and Leroleng. | SMV Consulting on behalf of Royal Bafokeng | 29 May2013 - 04 November 2013 | R 5 156 519.25 |
| Construction of a new Road in Robega | SMV Consulting Engineer | 11 November 2013 - 28 February 2014 | R 1 346 342.38 |
| Road construction in Mafenya 200m and Road construction in Mafenya 300m | Royal Bafokeng Platinum Mine | 10 July 2014 - 11/10/2014 | R 1 580 172.00 |
| Ikemeleng Bulk Roads Construction Phase4 | Rustenburg Local Municipality/MMM Consulting | 05 January 2015 - 31 July 2015 | R 6 448 074.27 |
| Construction of new interlocked paved Road in Robega. | Royal Bafokeng Platinum Mine | 13 July2015 - 13 October 2015 | R 2 277 683.36 |
| Construction of Internal Roads In Luka Village-Cluster B | Phatwe Consulting Engineers on behalf of Impala Platinum Mine | August 2017 | R 5 900 546.69 |
| Compressed Air line surface civil works package (Downcast Vent. Shaft) at Impala Mine 11Shaft | Hatch Consulting on behalf of Impala Platinum Mine | July 2018 | R 11 591 041.20 |
| Styldrift Ancillary Building and Civil works | Styldrift mine | July 2020 | R 4 323 765.34 |
| Vent Shaft 2 Small Civils | Styldrift mine | July 2020 | R 907 107.52 |